What we need to accelerate

Utility-scale

Large grid-connected wind, solar and storage. Built to sell into the wholesale market, normally underpinned by a corporate PPA or a government revenue contract.

grid-connected, above ~30 MW

Broken Hill solar plant, New South Wales. Jeremy Buckingham, CC BY 2.0

Where it gets stuck

Of the seven barriers the review found, these are the ones that slow this asset type down. The dark card is the one that slows it down most.

What slows it down mostApprovals & grid connection

Planning and environmental consent, and a place in the connection queue.

Also slows it downRevenue certainty

A contracted revenue matching project life that a lender will accept.

Also slows it downPortfolio allocation

Competition for capital within an institutional portfolio, and strategic asset allocation.

See all seven barriers, against all five asset types

What would unstick it

The interventions from the review that reach this asset type.

G5Live nowRegional pilot of centralised approvals

Blends the Sovereign Power proposal with an enhanced renewable energy zone approach. Government assesses and resolves land and native title once, then tenders prepared sites. More achievable than full sovereign power, and a pathway to it.

Government ask

G1Closing windowESEM design

Keep the Electricity Services Entry Mechanism simple and close to a straightforward government PPA. Contract a single large block of government demand first and fold in aggregated corporate demand later at a scheduled review. No change-of-policy termination rights. Embed it in the National Electricity Law.

Government ask

G7OngoingSIV mandate and operational reform

Reposition public capital earlier on the risk and development stage. Remove matched funding requirements at early stages. Harmonise applications so one process serves all specialist investment vehicles.

Government ask

J1Proposed; no ownerImproved coordination

Aligns government, investors and proponents around a shared agenda, and brings in the actors currently missing: planning ministers, large energy users, unions, traditional owners and super fund investment teams.

Joint government & ecosystem

E2Proposed; no ownerIndustry-funded communications

Sustained paid communications funded by the industry rather than carried by NGOs, with a mechanism that defeats free riding.

Ecosystem

See all fifteen interventions

Risks named in the review

Risks marked * were added in analysis rather than raised directly in the workshop record.

Case studies

Things that have already been tried, here and overseas, that bear on this asset type. Each carries a note on what its evidence does and does not support.

Open these in the full case study list

Who’s working on this

Loading…

Open the full directory, filtered to this asset type

Research and news

From the library and the daily brief, tagged to this asset type.

Where do you think the leverage is?

Fifteen interventions, five minutes. Place the ones you have a view on and you will see how everyone else has placed them.

Map the interventions